- Home
- DEPOSIT-Kochi Corporation-Replacing old...
DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work
Project |
DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work |
Project Code |
EKMDEPO122315787 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Vytilla Section 1 |
AS Amount (Rs) |
850000
|
AS Number |
CCPC7-1154/22 |
TS Amount (Rs) |
850000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/25325/2023_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
200 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
60% completed |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Kochi Corporation-Replacing old and damaged 100mm AC pipe line by 110mm PVC pipe line in Puthiya Road to improve water supply in division no. 43(new) 32(old) of Kochi Corporation-Pipeline Work |
Vytilla Section 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Apr 2024 |
E bill submitted |
Vytilla Section AE - 1 |
|
04 Apr 2024 |
Reconcreting completed |
Vytilla Section AE - 1 |
|
01 Apr 2024 |
Reconcreting in progress |
Vytilla Section AE - 1 |
|
23 Mar 2024 |
GSB laying completed |
Vytilla Section AE - 1 |
|
19 Mar 2024 |
GSB laying completed |
Vytilla Section AE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/03/2024 |
Scheduled date of Completion of the Project |
31 May 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
22 Dec 2023 |
TS Date |
02 Feb 2024 |