JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS
Project |
JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS |
Project Code |
KNRJJM022210836 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
300 mm DI K9 Gravity main, 12 LL ,2LL,1.5LL Reservoirs,Pumping mains, Laying distribution system and providing FHTCs |
Status |
On-going |
District |
Kannur |
Executing Office |
Mattannur Project Dn |
AS Amount (Rs) |
925100000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
841500000 |
TS Number |
9879/2022-2023 |
Total Bill Submitted (Rs) |
319857883 |
Total Bill Paid (Rs) |
319639063 |
Population Benefitted |
33893 |
Capacity in MLD |
3.90 |
Actual Project Completion Date |
19 Sep 2023 |
Coverage |
5639 Nos FHTCs
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS |
Mattannur Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2023 |
Pipe Laying and HTC work is on progress.GLSR 2LL capacity at vilamana.OHSR 1.5LL at Mattinithattu and 12LL GLSR AT Mattini work is on progress |
Mattannur Project Sn 2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/09/2022 |
Scheduled date of Completion of the Project |
19 Sep 2023 |
Expected date of Completion |
30/04/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
12 Jul 2022 |