Project | JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS |
---|---|
Project Code | KNRJJM022210836P1 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying gravity main from OHSR at Iritty HSS to Sump at Malapottu, Construction of 2 LL sump Malapottu, 12 ll GLSR at Vilamana , 1.5 LL OHSR at Mattinithattu, 195 km s distribution system in whole area of Payam Panchayath , 5639 Nos FHTCs including PWD & LSGD road reformation |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 841500000 |
TS Number | 9879/2022-2023 |
Technical specification | Laying gravity main from OHSR at Iritty HSS to Sump at Malapottu, Construction of 2 LL sump Malapottu, 12 ll GLSR at Vilamana , 1.5 LL OHSR at Mattinithattu, 195 km s distribution system in whole area of Payam Panchayath , 5639 Nos FHTCs including PWD & LSGD road reformation |
Contractor | BABURAJ P K (Mob: 9447152707) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/09/2022 |
---|---|
Scheduled date of Completion as per agreement | 19 Sep 2023 |
Expected date of Completion | 31/03/2025 |
TS Date | 12 Jul 2022 |
---|---|
Estimate Approval | 12 Jul 2022 |
NIT Approval | 05 Sep 2022 |
Tender Closing | 18 Jul 2022 |
Technichal Pre-Qualification | 05 Sep 2022 |
Price bid opening | 13 Sep 2022 |
Workorder Date | 20 Sep 2022 |
---|---|
NA | 06 Oct 0022 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 91% Completed
Earth excavation and Pipe laying is in progress. 259 km pipe laying completed out of total 287.43 km . Reservoirs of 1.5 LL OHSR at mattinithattu,2.0 LL GLSR booster sump cum Pump House at Vilamana ,12 LL GLSR at Mattini completed. House connection work is in progress.4850 HTC Completed.in that 3786 nos. connections tagging completed. PVC PIPE of 90mm 10 kg(Parallel) laying is in progress at Iritty - Kootupuzha road,500 DI laying work completed at Madathil-Vallithode road. KSEB HT,LT connection work is awaiting. Gravity main from iritty HSS Tank to Vilamana sump completed. HDPE river crossing completed and trial running and scouring completed up to vilamana sump .Road restoration is progress in Malayora highway 6km completed. 2LL capacity vilamana booster station Transformer land has to be handed over by Panchayath,land agreement paper work under progress. 300 mm DI laying work in progress at Keelanpeedika-Udayagiri Road.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 91% Completed
Earth excavation and Pipe laying is in progress. 258.5 km pipe laying completed out of total 287.43 km . Reservoirs of 1.5 LL OHSR at mattinithattu,2.0 LL GLSR booster sump cum Pump House at Vilamana ,12 LL GLSR at Mattini completed. House connection work is in progress.4850 HTC Completed.in that 3786 nos. connections tagging completed. PVC PIPE of 90mm 10 kg(Parallel) laying is in progress at Iritty - Kootupuzha road,500 DI laying work completed at Madathil-Vallithode road. KSEB HT,LT connection work is awaiting. Gravity main from iritty HSS Tank to Vilamana sump completed. HDPE river crossing completed and trial running and scouring completed up to vilamana sump .Road restoration is progress in Malayora highway 6km completed. 2LL capacity vilamana booster station Transformer land has to be handed over by Panchayath,land agreement paper work under progress. 300 mm DI laying work in progress at Keelanpeedika-Udayagiri Road.