JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS

Project JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS
Project Code KNRJJM022210836P1
Type Package
Main Project JJM-KANNUR DISTRICT-PAYAM GRAMA PANCHAYATH-WSS TO MATTANNUR ,IRITTY AND ADJOINING PANCHAYATHS-PHASE III- LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying gravity main from OHSR at Iritty HSS to Sump at Malapottu, Construction of 2 LL sump Malapottu, 12 ll GLSR at Vilamana , 1.5 LL OHSR at Mattinithattu, 195 km s distribution system in whole area of Payam Panchayath , 5639 Nos FHTCs including PWD & LSGD road reformation
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 841500000
TS Number 9879/2022-2023
Technical specification Laying gravity main from OHSR at Iritty HSS to Sump at Malapottu, Construction of 2 LL sump Malapottu, 12 ll GLSR at Vilamana , 1.5 LL OHSR at Mattinithattu, 195 km s distribution system in whole area of Payam Panchayath , 5639 Nos FHTCs including PWD & LSGD road reformation
Contractor BABURAJ P K (Mob: 9447152707)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/09/2022
Scheduled date of Completion as per agreement 19 Sep 2023
Expected date of Completion 31/03/2025

Processing Dates

TS Date 12 Jul 2022
Estimate Approval 12 Jul 2022
NIT Approval 05 Sep 2022
Tender Closing 18 Jul 2022
Technichal Pre-Qualification 05 Sep 2022
Price bid opening 13 Sep 2022

Approval Dates

Workorder Date 20 Sep 2022
NA 06 Oct 0022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 91% Completed

Earth excavation and Pipe laying is in progress. 259 km pipe laying completed out of total 287.43 km . Reservoirs of 1.5 LL OHSR at mattinithattu,2.0 LL GLSR booster sump cum Pump House at Vilamana ,12 LL GLSR at Mattini completed. House connection work is in progress.4850 HTC Completed.in that 3786 nos. connections tagging completed. PVC PIPE of 90mm 10 kg(Parallel) laying is in progress at Iritty - Kootupuzha road,500 DI laying work completed at Madathil-Vallithode road. KSEB HT,LT connection work is awaiting. Gravity main from iritty HSS Tank to Vilamana sump completed. HDPE river crossing completed and trial running and scouring completed up to vilamana sump .Road restoration is progress in Malayora highway 6km completed. 2LL capacity vilamana booster station Transformer land has to be handed over by Panchayath,land agreement paper work under progress. 300 mm DI laying work in progress at Keelanpeedika-Udayagiri Road.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 91% Completed

Earth excavation and Pipe laying is in progress. 258.5 km pipe laying completed out of total 287.43 km . Reservoirs of 1.5 LL OHSR at mattinithattu,2.0 LL GLSR booster sump cum Pump House at Vilamana ,12 LL GLSR at Mattini completed. House connection work is in progress.4850 HTC Completed.in that 3786 nos. connections tagging completed. PVC PIPE of 90mm 10 kg(Parallel) laying is in progress at Iritty - Kootupuzha road,500 DI laying work completed at Madathil-Vallithode road. KSEB HT,LT connection work is awaiting. Gravity main from iritty HSS Tank to Vilamana sump completed. HDPE river crossing completed and trial running and scouring completed up to vilamana sump .Road restoration is progress in Malayora highway 6km completed. 2LL capacity vilamana booster station Transformer land has to be handed over by Panchayath,land agreement paper work under progress. 300 mm DI laying work in progress at Keelanpeedika-Udayagiri Road.