Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath

Project Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath
Project Code CLTJJM08206097P1
Type Package
Main Project Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 7112 Nos FHTCs by laying new distribution lines in Perambra Grama Panchayath. Supplying, laying, testing and commissioning of DI pipe of diameter 450mm-900m,400mm- 460m,350mm- 810m,300mm- 2320m ,250mm-3060m, 200mm- 3200m and PVC pipes of diameter 90mm -86710m (including rider lines along DI pipes and along both sides of major roads) 110mm -10000m ,140mm-2160m and 160mm -5670m
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 306900000
TS Number TS/10193/2020-2021
Technical specification Providing 7112 Nos FHTCs by laying new distribution lines in Perambra Grama Panchayath. Supplying, laying, testing and commissioning of DI pipe of diameter 450mm-900m,400mm- 460m,350mm- 810m,300mm- 2320m ,250mm-3060m, 200mm- 3200m and PVC pipes of diameter 90mm -86710m (including rider lines along DI pipes and along both sides of major roads) 110mm -10000m ,140mm-2160m and 160mm -5670m
Contractor Koya & Company Construction Limited (Mob: 9447885004)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
25 Mar 2022 Pending Pending Road Cut Related Risk Road cutting permission to be obtained for 1.Perambra junction to chaniyamkadavu 9 km (KRFB) No comments available. Pending
11 Jan 2022 Pending Pending Road Cut Related Risk Road cutting permission to be obtained for Peramabra - Payyoli road -936 m (Both sides of the road) (KRFB) No comments available. Pending
10 Jun 2021 Pending Pending Road Cut Related Risk 1.Kaithakkal -last kallode road -4300m both sides of the road 2.Chaniyam kadavu jn -Vatakara road -RHS -4125m,LHS 3340m 3.Chaniyam kadavu jn -Payyoli road-1600m on both sides of the road No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/01/2021
Scheduled date of Completion as per agreement 31 Dec 2021
Expected date of Completion 31/05/2024

Processing Dates

TS Date 28 Oct 2020
Estimate Approval 28 Oct 2020
NIT Approval 30 Oct 2020
Tender Closing 17 Dec 2020
Technichal Pre-Qualification 22 Dec 2020
Price bid opening 24 Dec 2020

Approval Dates

Workorder Date 01 Jan 2021
NA 16 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE4
Date: 17/05/2024

Work in progress | 95% Completed

Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3360 HTCs provided, Charging Work in progress. .

Kozhikode Project Dn AE4
Date: 14/05/2024

Work in progress | 95% Completed

Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3360 HTCs provided, Charging Work in progress. .