Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath

Project Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath
Project Code CLTJJM08206097
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 7112 Nos FHTCs by laying new distribution lines in Perambra Grama Panchayath. Supplying, laying, testing and commissioning of DI pipe of diameter 450mm-900m,400mm- 460m,350mm- 810m,300mm- 2320m ,250mm-3060m, 200mm- 3200m and PVC pipes of diameter 90mm -86710m (including rider lines along DI pipes and along both sides of major roads) 110mm -10000m ,140mm-2160m and 160mm -5670m
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 323800000
AS Number ASNO.GO(Rt)No.541/2020
TS Amount (Rs) 306900000
TS Number TS/2020-2021/2020/20890
Total Bill Submitted (Rs) 257149725
Total Bill Paid (Rs) 257149725
Population Benefitted 35560
Capacity in MLD 3.00
Actual Project Completion Date 29 Feb 2024
Coverage Perambra Grama Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission: 2020-21 (Phase1) - Perambra Grama Panchayath in Kozhikode District – Providing Functional Household Tap Connections by Augmentation of Ongoing Water Supply Scheme in Perambra Panchayath Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2024 Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3360 HTCs provided, Charging Work in progress. Kozhikode Project Dn AE5
30 Jan 2024 Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3360 HTCs provided, Charging Work in progress. Kozhikode Project Dn AE5
02 Jan 2024 Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3360 HTCs provided, Charging Work in progress. Kozhikode Project Dn AE5
01 Dec 2023 Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3300 HTCs provided, Charging Work in progress. Kozhikode Project Dn AE5
01 Nov 2023 Pipes laid (1)90 mm PVC -79440m 2)110mm PVC -7500m 3)140 mm PVC -1375.5m 4)160 mm PVC-5100m ,5)250 mm DI -2741m, 6) 400 mm DI - 440.93m 7) 350 mm DI-800m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -840m), Total pipe laid =102195.74m, House connection work in progress. 1245 FHTCs and 3300 HTCs provided, Charging Work in progress. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/01/2021
Scheduled date of Completion of the Project 31 Dec 2021
Expected date of Completion 30/04/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 28 Oct 2020

Other details

Project Officers View