AWSS to Kollam Corporation - Improvements to water supply in Thamarakulam & Mundakkal Zone - Construction of 8 LL OHSR in Mundakkal, 1 LL Sump, Providing 2 nos 20 hp pumpsets,Providing transmission main to Mundakkal for 1500m using 250mm DI pipe, including road restoration charges
| Project |
AWSS to Kollam Corporation - Improvements to water supply in Thamarakulam & Mundakkal Zone - Construction of 8 LL OHSR in Mundakkal, 1 LL Sump, Providing 2 nos 20 hp pumpsets,Providing transmission main to Mundakkal for 1500m using 250mm DI pipe, including road restoration charges |
| Project Code |
KLMAMRUT112214153P5 |
| Type |
Package |
| Main Project |
AMRUT - 2.0 - Augmentation of Water Supply To Kollam Corporation – Distribution Improvements
|
| Funding Agency |
AMRUT |
| Category |
AMRUT 2 |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
Improvements to water supply in Thamarakulam & Mundakkal Zone by constructing 8 LL OHSR in Mundakkal, 1 LL Sump, Providing 2 nos 20 hp pump sets, Providing transmission main to Mundakkal for 1500m using 250mm DI pipe |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kollam Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
0 |
| TS Number |
|
| Technical specification |
|
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
21/04/2023 |
| Scheduled date of Completion as per agreement |
11 Oct 2024 |
| Expected date of Completion |
11/10/2024 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Kollam Project Dn EE |
| Date: 12/05/2025 |
Work in progress | 0% Completed
The work for closure as per order no. KWA/PHC/KLM/D2/5468/2023 dated 10/03/2025.
.
| Kollam Project Dn EE |
| Date: 05/05/2025 |
Work has started | 0% Completed
The work for closure as per order no. KWA/PHC/KLM/D2/5468/2023 dated 10/03/2025..