Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II
| Project |
Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II |
| Project Code |
KNRJJM08202989 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
Jal Jeevan Mission - Kannur district - Chapparappadavu
Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II
|
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Thaliparambu WS Dn |
| AS Amount (Rs) |
96000000
|
| AS Number |
G.O.(Rt)No.541/WRD/2020 |
| TS Amount (Rs) |
86600000 |
| TS Number |
11110/2020-2021 |
| Total Bill Submitted (Rs) |
50873253 |
| Total Bill Paid (Rs) |
50873253 |
| Population Benefitted |
19400 |
| Capacity in MLD |
1.30 |
| Actual Project Completion Date |
30 Nov 2022 |
| Coverage |
Chapparappadavu Panchayath - koovery village |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II-Zone III- Mangara, Koovery Kattaampally adj. areas and areas Adj Kuppam River- P3 |
Thaliparamba WS Sn |
|
| 2 |
Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II-Zone II- Madamthattu Distribution areas- P2 |
Thaliparamba WS Sn |
|
| 3 |
Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II- Zone I - Nadukani and Madakkad distribution areas- P1 |
Thaliparamba WS Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 28 Dec 2022 |
completed |
Thaliparamba WS Dn EE |
|
| 23 Dec 2022 |
2661 FHTCs completed |
Payyannur WS Sn - AE |
|
| 19 Dec 2022 |
2661 FHTCs completed |
Payyannur WS Sn - AE |
|
| 15 Dec 2022 |
FHTCs completed |
Payyannur WS Sn - AE |
|
| 12 Dec 2022 |
2661 FHTCs completed |
Payyannur WS Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
21/06/2021 |
| Scheduled date of Completion of the Project |
30 Nov 2021 |
| Expected date of Completion |
31/05/2022 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
27 Aug 2020 |