| Project | Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II-Zone II- Madamthattu Distribution areas- P2 |
|---|---|
| Project Code | KNRJJM08202989P2 |
| Type | Package |
| Main Project | Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission-Kannur district-Chapparappadavu Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II-Zone II- Madamthattu Distribution areas- P2 |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 28900000 |
| TS Number | 11109/2020-2021 |
| Technical specification | 1294 FHTC, 90 mm PVC -2500m,75 mm PVC-700m and 90 mm PE pipe 3000m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/07/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 02 Sep 2021 |
| Expected date of Completion | 30/06/2022 |
| TS Date | 19 Nov 2020 |
|---|---|
| Estimate Approval | 19 Nov 2020 |
| Tender Closing | 30 Apr 2021 |
| Price bid opening | 01 May 2021 |
| Workorder Date | 06 May 2021 |
|---|---|
| NA | 21 Jun 2021 |
| Thaliparamba WS Dn EE |
| Date: 28/12/2022 |
Work has been completed | 100% Completed
904 FHTCs completed.
| Thaliparamba WS Dn EE |
| Date: 19/12/2022 |
Work in progress | 68% Completed
891/1293 FHTCs complete .