Project | JJM Phase II - CWSS to Sulthan Bathery Municipality Noolpuzha and Muttil Panchayaths in Wayanad Phase 3 - Extending distribution line and providing FHTC in NOOLPUZHA GP (4thSWSM 4969 FHTC) |
---|---|
Project Code | CLTJJM022211023P1 |
Type | Package |
Main Project | Jal Jeevan Mission-Cwss To Sulthanbathery, Noolpuzha And Muttil Scheme- Phase III - Laying , Distribution And Providing FHTCs in MUTTIL & NOOLPUZHA Panchayaths. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | providing FHTC in NOOLPUZHA GP (4thSWSM 4969 FHTC) |
Status | On-going |
District | Wayanad |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 243000000 |
TS Number | TS/2022-2023/2022/24288 |
Technical specification | Providing 4969 FHTCs |
Contractor | KT.Manoj (Mob: 7558043708) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Feb 2023 | Pending | Pending | Road Cut Related Risk | Road cutting permission denied for pipe laying in NH 766, Sultan Bathery to Muthanga | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 21 Mar 2023 |
Expected date of Completion | 31/03/2024 |
TS Date | 08 Jul 2022 |
---|---|
Estimate Approval | 08 Jul 2022 |
Tender Closing | 06 Aug 2022 |
Price bid opening | 09 Aug 2022 |
Workorder Date | 22 Sep 2022 |
---|---|
NA | 06 Oct 2022 |
Kozhikode Project Dn AE4 |
Date: 15/05/2024 |
Work in progress | 94% Completed
Total pipe to be laid - 155016m / Supplied - 154206 / laid - 143076 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0.
Kozhikode Project Dn AE4 |
Date: 14/05/2024 |
Work in progress | 94% Completed
Total pipe to be laid - 155016m / Supplied - 154206 / laid - 143076 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0.