Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission-Cwss To Sulthanbathery, Noolpuzha And Muttil Scheme- Phase III - Laying , Distribution And Providing FHTCs in MUTTIL & NOOLPUZHA Panchayaths.

Project Jal Jeevan Mission-Cwss To Sulthanbathery, Noolpuzha And Muttil Scheme- Phase III - Laying , Distribution And Providing FHTCs in MUTTIL & NOOLPUZHA Panchayaths.
Project Code CLTJJM022211023
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description 1. Laying distribution lines from Vadachira 9LL OHSR using 90mm PE pipe 63049m, 110mm PE pipe 97m, 125mm PE pipe 456m, 160mm PE pipe 7350m. 2. Laying distribution lines from 7LL OHSR at Nirapath using 90mm PE pipe 74050m, 110mm PE pipe 262m, 125mm PE pipe 3989m, 160mm PE pipe 5763m. 3. Providing 4969 FHTC.
Status On-going
District Wayanad
Executing Office Kozhikode Project Dn
AS Amount (Rs) 663600000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 243000000
TS Number TS/2022-2023/2022/24288
Total Bill Submitted (Rs) 77556929
Total Bill Paid (Rs) 77556929
Population Benefitted 33523
Capacity in MLD 16.00
Actual Project Completion Date Date is not specified
Coverage MUTTIL & NOOLPUZHA Panchayaths.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM Phase II - CWSS to Sulthan Bathery Municipality Noolpuzha and Muttil Panchayaths in Wayanad Phase 3 - Extending distribution line and providing FHTC in NOOLPUZHA GP (4thSWSM 4969 FHTC) Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Mar 2024 Noolpuzha GP- Total pipe to be laid - 155016m / Supplied - 154206/ laid - 143076 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0. Kozhikode Project Dn AE4
18 Jan 2024 Noolpuzha GP- Total pipe to be laid - 155016m / Supplied - 154206/ laid - 142828 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0. Kozhikode Project Dn AE4
12 Jan 2024 Noolpuzha GP- Total pipe to be laid - 155016m / Supplied - 154206/ laid - 142828 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0. Kozhikode Project Dn AE4
12 Feb 2024 Noolpuzha GP- Total pipe to be laid - 155016m / Supplied - 154206/ laid - 142828 . Total FHTC to be given 4969 / HTC given 3300, FHTC - 0. Kozhikode Project Dn AE4
14 Dec 2023 Noolpuzha GP- Total pipe to be laid - 155016m / Supplied - 154206/ laid - 135464 . Total FHTC to be given 4969 / HTC given 3000, FHTC - 0. Kozhikode Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/10/2022
Scheduled date of Completion of the Project 21 Mar 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 08 Jul 2022

Other details

Project Officers View