Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath

Project Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Project Code WYDDEPO042211573P1
Type Package
Main Project Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 610000
TS Number WRD/KWA-CE(NR)/EST_TS/8541/2022_26_1_1
Technical specification Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/05/2022
Scheduled date of Completion as per agreement 21 Nov 2022
Expected date of Completion 31/12/2022

Processing Dates

TS Date 10 Jul 2023
Estimate Approval 30 May 2022
NIT Approval 10 Jul 2023
Tender Closing 01 Aug 2023
Technichal Pre-Qualification 01 Aug 2023
Price bid opening 02 Aug 2023

Approval Dates

Workorder Date 18 Aug 2023
NA 21 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 14/03/2024

Work has been completed | 100% Completed

Work completed and Bill submitted..

Sulthan Bathery PH Dn EE
Date: 15/02/2024

Work has been completed | 100% Completed

Work completed..