Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Project |
Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath |
Project Code |
WYDDEPO042211573 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath |
Status |
Completed |
District |
Wayanad |
Executing Office |
Sulthan Bathery Sn |
AS Amount (Rs) |
610000
|
AS Number |
A2-501/21 |
TS Amount (Rs) |
610000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/8541/2022_26_1_1 |
Total Bill Submitted (Rs) |
132079 |
Total Bill Paid (Rs) |
132079 |
Population Benefitted |
1000 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
30 Nov 2023 |
Coverage |
Ambalavayal Villages |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath |
Sulthan Bathery Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Mar 2024 |
Work completed and Bill submitted. |
Sulthan Bathery PH Dn EE |
|
15 Feb 2024 |
Work completed. |
Sulthan Bathery PH Dn EE |
|
07 Feb 2024 |
Site handed over. |
Sulthan Bathery PH Dn EE |
|
30 Jan 2024 |
Site handed over. |
Sulthan Bathery PH Dn EE |
|
22 Jan 2024 |
Site handed over. |
Sulthan Bathery PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/05/2022 |
Scheduled date of Completion of the Project |
20 Nov 2023 |
Expected date of Completion |
29/02/2024 |
Processing Dates
AS Date |
30 May 2022 |
TS Date |
10 Jul 2023 |