Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath

Project Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Project Code WYDDEPO042211573
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath
Status Completed
District Wayanad
Executing Office Sulthan Bathery Sn
AS Amount (Rs) 610000
AS Number A2-501/21
TS Amount (Rs) 610000
TS Number WRD/KWA-CE(NR)/EST_TS/8541/2022_26_1_1
Total Bill Submitted (Rs) 132079
Total Bill Paid (Rs) 132079
Population Benefitted 1000
Capacity in MLD 10.00
Actual Project Completion Date 30 Nov 2023
Coverage Ambalavayal Villages
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work (2021-22)- ARWSS to Krishnagiri Purakadi and Ambalavayal Villages-Relaying of 250mm DI Pumping Main along Cheeramkunnu-Murani road in Ward No.9 in Meenangadi panchayath Sulthan Bathery Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Mar 2024 Work completed and Bill submitted. Sulthan Bathery PH Dn EE
15 Feb 2024 Work completed. Sulthan Bathery PH Dn EE
07 Feb 2024 Site handed over. Sulthan Bathery PH Dn EE
30 Jan 2024 Site handed over. Sulthan Bathery PH Dn EE
22 Jan 2024 Site handed over. Sulthan Bathery PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 30/05/2022
Scheduled date of Completion of the Project 20 Nov 2023
Expected date of Completion 29/02/2024

Processing Dates

AS Date 30 May 2022
TS Date 10 Jul 2023

Other details

Project Officers View