Project | DW - Kochi Corporation - Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
---|---|
Project Code | EKMGOK11208051 |
Type | Main project |
Funding Agency | GOK |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | DW - Kochi Corporation - Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
Status | Completed |
District | Ernakulam |
Executing Office | Karuvelippady WW Sn 2 |
AS Amount (Rs) | 120000 |
AS Number | A1-495/2020 |
TS Amount (Rs) | 120000 |
TS Number | 2020-21/2019/16505 |
Total Bill Submitted (Rs) | 70240 |
Total Bill Paid (Rs) | 70240 |
Population Benefitted | 2200 |
Capacity in MLD | 22.00 |
Actual Project Completion Date | 31 Dec 2021 |
Coverage | Ilayachan parambu in Div.07 |
Implementation Schedule | Download |
Work Plan | Download |
Review Date | Review Message | Review Attended By |
---|---|---|
30 Apr 2021 | Work not started due to delay in getting pipe. |
Date of start of Project | 25/02/2020 |
---|---|
Scheduled date of Completion of the Project | 30 Apr 2021 |
Expected date of Completion | 31/12/2021 |
AS Date | 25 Feb 2020 |
---|---|
TS Date | 02 Dec 2020 |
Project Officers | View |
---|