Project | DW - Kochi Corporation - Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
---|---|
Project Code | EKMGOK11208051P1 |
Type | Package |
Main Project | DW - Kochi Corporation - Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
Funding Agency | GOK |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | DW - Kochi Corporation - Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
Status | On-going |
District | Ernakulam |
Executing Office | Karuvelippady WW Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 120000 |
TS Number | 2020-21/2019/16505 |
Technical specification | Laying 75mm PVC pipe for a length of 96m for improving water supply at Ilayachan parambu in div.07 of Kochi Corporation |
Contractor | Anilkumar S (Mob: 9446969477) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/02/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Apr 2021 |
Expected date of Completion | 31/12/2021 |
TS Date | 02 Dec 2020 |
---|---|
Estimate Approval | 02 Dec 2020 |
NIT Approval | 15 Jan 2021 |
Tender Closing | 18 Jan 2021 |
Technichal Pre-Qualification | 23 Mar 2021 |
Price bid opening | 23 Mar 2021 |
Workorder Date | 23 Mar 2021 |
---|---|
NA | 15 Apr 2021 |
Karuvelippady AEE |
Date: 16/09/2022 |
Work has been completed | 100% Completed
Payment made.
Karuvelippady AEE |
Date: 15/09/2022 |
Work has been completed | 100% Completed
Payment made .