CWSS to Mannur,Keralassery and Mankara panchayaths of Palakkad District -Phase-I

Project CWSS to Mannur,Keralassery and Mankara panchayaths of Palakkad District -Phase-I
Project Code PKDNABARD1217641P1
Type Package
Main Project NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALASSERY AND MANKARA PANCHAYTHS IN PALAKKAD DISTRICT
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Construction of 10MLD WTP,11LL OHSR For Mannur ,8LL OHSR , 2.60LL C W Sump ,R/W and C/W pumpingmains . Supplying and errection of motor pumpsets,Transformer &allied works
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 253000000
TS Number TS/2018-2019/2018/158
Technical specification 400mm DIk9 RWPM-5740m 350mm DIK9 CWPM-4965m 200mm DIK9 CWPM-6100m WTP-10mld 11LL OHSR for Mannur 8LL OHSR for Keralassery 2.66LL CW Sump for Keralassery RW pumpset at Well- 3Nos 58mx53lps-60hp CW pumpset at WTP-2Nos of 21mx67lps-30hp CW pumpset- 2Nos of 64mx26lps for Keralassery-40hp CW pumpset-2Nos of 28mx34lps for Mannur-25hp
Contractor Binumathew (Mob: 9446462010)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/01/2019
Scheduled date of Completion as per agreement 31 Mar 2021
Expected date of Completion 29/10/2021

Processing Dates

TS Date 10 Apr 2018
Estimate Approval 17 Apr 2018
NIT Approval 11 May 2021
Tender Closing 26 May 2018
Technichal Pre-Qualification 11 May 2018
Price bid opening 26 May 2018

Approval Dates

NA 21 Nov 2018
Workorder Date 24 Oct 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj Dn AE 4
Date: 04/12/2021

Work has been completed | 100% Completed

work completed.

Palakkad Proj Dn AE 4
Date: 03/12/2021

Work has been completed | 100% Completed

Final bill under preparation.