- Home
- CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(...
CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084)
| Project |
CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084) |
| Project Code |
KLMGOI0713492 |
| Type |
Main project |
| Funding Agency |
GOI |
| Category |
ARP Central |
| Type of scheme |
Water Supply |
| Scheme |
|
| Description |
"a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m
b)20 HP centrifugal pump sets -2nos
c)4 Lakh Litre OHSR at Kalyani Junction
|
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Kollam Project Dn |
| AS Amount (Rs) |
181500000
|
| AS Number |
KWA/JB/WS1/44/02 VOL IV |
| TS Amount (Rs) |
38000000 |
| TS Number |
TS/2018-2019/2018/12008 |
| Total Bill Submitted (Rs) |
21546456 |
| Total Bill Paid (Rs) |
21546456 |
| Population Benefitted |
145479 |
| Capacity in MLD |
2.70 |
| Actual Project Completion Date |
30 Sep 2021 |
| Coverage |
Punaloor constituency Part 145479 Population |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction |
Kollam Project Dn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 Sep 2021 |
1. Plastering works for tank in progress 2. Work for chambers of pumping main in progress 3. Work for erection of pump sets in progress |
Kollam Project HD |
|
| 15 Sep 2021 |
1. Plastering works for tank in progress 2. Work for chambers of pumping main in progress 3. Work for erection of pump sets in progress |
Kollam Project HD |
|
| 10 Sep 2021 |
1. Plastering works for tank in progress
2. Work for chambers of pumping main in progress
3. Work for erection of pump sets in progress |
Kollam Project HD |
|
| 06 Sep 2021 |
1.Plastering works for OHSR in progress
|
Kollam Project HD |
|
| 03 Sep 2021 |
Plastering works and tank cleaning for plastering in progress..Laying of double flanged pipes also in progress..valve chamber works in progress |
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
09/09/2020 |
| Scheduled date of Completion of the Project |
27 Feb 2021 |
| Expected date of Completion |
30/09/2021 |
Processing Dates
| AS Date |
06 Jul 2013 |
| TS Date |
07 Mar 2019 |