Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084)

Project CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084)
Project Code KLMGOI0713492
Type Main project
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description "a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction
Status Completed
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 181500000
AS Number KWA/JB/WS1/44/02 VOL IV
TS Amount (Rs) 38000000
TS Number TS/2018-2019/2018/12008
Total Bill Submitted (Rs) 21546456
Total Bill Paid (Rs) 21546456
Population Benefitted 145479
Capacity in MLD 2.70
Actual Project Completion Date 30 Sep 2021
Coverage Punaloor constituency Part 145479 Population
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Sep 2021 1. Plastering works for tank in progress 2. Work for chambers of pumping main in progress 3. Work for erection of pump sets in progress Kollam Project HD
15 Sep 2021 1. Plastering works for tank in progress 2. Work for chambers of pumping main in progress 3. Work for erection of pump sets in progress Kollam Project HD
10 Sep 2021 1. Plastering works for tank in progress 2. Work for chambers of pumping main in progress 3. Work for erection of pump sets in progress Kollam Project HD
06 Sep 2021 1.Plastering works for OHSR in progress Kollam Project HD
03 Sep 2021 Plastering works and tank cleaning for plastering in progress..Laying of double flanged pipes also in progress..valve chamber works in progress Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/09/2020
Scheduled date of Completion of the Project 27 Feb 2021
Expected date of Completion 30/09/2021

Processing Dates

AS Date 06 Jul 2013
TS Date 07 Mar 2019

Other details

Project Officers View