"CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction

Project "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction
Project Code KLMGOI0713492P1
Type Package
Main Project CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084)
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction AS of 10 crores obtained on 1.11.2012 and Balance AS of Rs.8.15 crore obtained on 06.07.2013
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 38000000
TS Number TS/2018-2019/2018/12008
Technical specification a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/09/2020
Scheduled date of Completion as per agreement 30 May 2021
Expected date of Completion 30/09/2021

Processing Dates

TS Date 07 Mar 2019
Estimate Approval 07 Mar 2019
NIT Approval 23 May 2019
Supplying and Laying 01 Aug 2019
Tender Closing 29 May 2019
Technichal Pre-Qualification 08 Jun 2019
Price bid opening 12 Jun 2019

Approval Dates

CE Approval 08 Jul 2019
Head Office Approval 08 Jul 2019
Board Approval 08 Jul 2019
Final Approval 08 Jul 2019
Workorder Date 17 Jul 2019
NA 01 Aug 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 30/09/2021

Work has been completed | 100% Completed

Works for painting and plaster completed.Trail running and commissioning pending -due to non availablilty of power connection.

Kollam Project HD
Date: 29/09/2021

Work in progress | 98% Completed

Painting works in progress.