| Project | "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction |
|---|---|
| Project Code | KLMGOI0713492P1 |
| Type | Package |
| Main Project | CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-RWSS to Kulathuppuzha and Adjoining Panchayaths Phase II and Phase II Revised(1084) |
| Funding Agency | GOI |
| Category | ARP Central |
| Type of scheme | Water Supply |
| Scheme | |
| Description | "CARWSS to Kulathupuzha and Adjoining Villages-PhaseII and PhaseII Revised " a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction AS of 10 crores obtained on 1.11.2012 and Balance AS of Rs.8.15 crore obtained on 06.07.2013 |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 38000000 |
| TS Number | TS/2018-2019/2018/12008 |
| Technical specification | a)200mm DIK9 pumping main from Thottamukku sump to 4L.L.OHSR at Kalyani Junction-5200m b)20 HP centrifugal pump sets -2nos c)4 Lakh Litre OHSR at Kalyani Junction |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/09/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 30 May 2021 |
| Expected date of Completion | 30/09/2021 |
| TS Date | 07 Mar 2019 |
|---|---|
| Estimate Approval | 07 Mar 2019 |
| NIT Approval | 23 May 2019 |
| Supplying and Laying | 01 Aug 2019 |
| Tender Closing | 29 May 2019 |
| Technichal Pre-Qualification | 08 Jun 2019 |
| Price bid opening | 12 Jun 2019 |
| CE Approval | 08 Jul 2019 |
|---|---|
| Head Office Approval | 08 Jul 2019 |
| Board Approval | 08 Jul 2019 |
| Final Approval | 08 Jul 2019 |
| Workorder Date | 17 Jul 2019 |
| NA | 01 Aug 2019 |
| Kollam Project HD |
| Date: 30/09/2021 |
Work has been completed | 100% Completed
Works for painting and plaster completed.Trail running and commissioning pending -due to non availablilty of power connection.
| Kollam Project HD |
| Date: 29/09/2021 |
Work in progress | 98% Completed
Painting works in progress.