AMRUT - WSS to Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone - Package - I.

Project AMRUT - WSS to Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone - Package - I.
Project Code KNRAMRUT12173132P1
Type Package
Main Project AMRUT - Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone
Status On-going
District Kannur
Executing Office Kannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/10/2018
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 15/08/2020

Processing Dates

AS Date 23 Dec 2017
TS Date 09 Jan 2018
Estimate Approval 09 Jan 2018

Approval Dates

Workorder Date 17 May 2018
NA 06 Jun 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 14/09/2020

Work has been completed | 100% Completed

Work completed and commissioned .new house connection work in progress.