AMRUT - Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone

Project AMRUT - Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone
Project Code KNRAMRUT12173132
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone of Kannur Corporation. Distribution line total length 17285 m-(400 mm DI 240 m,350 mm DI 400 m,300 mm DI 405 m,250mm DI 3285 m,200mm DI 10195m ,150 mm DI 2760 m)
Status Completed
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 89500000
AS Number
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 79508548
Total Bill Paid (Rs) 91908548
Population Benefitted 40818
Capacity in MLD 8.80
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT - WSS to Kannur Corporation - Rehabilitation of existing old distribution networks, valves, house service connection and inter connection with existing lines of Edakkad zone - Package - I. Kannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Sep 2020 100 % complted Koothuparamba Proj AE 2
12 Sep 2020 Work completed and commissioned. New house connection in progress. Koothuparamba Proj AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/10/2018
Scheduled date of Completion of the Project 16 May 2019
Expected date of Completion 31/12/2020

Processing Dates

AS Date 23 Dec 2017
TS Date 09 Jan 2018
Estimate Approval 09 Jan 2018
Tender Closing 14 Feb 2018
Technichal Pre-Qualification 09 Mar 2018
Price bid opening 09 Mar 2018

Approval Dates

Head Office Approval 11 May 2018
Final Approval 17 May 2018
Workorder Date 17 May 2018
NA 06 Jun 2018

Other details