| Project | Project VI KIIFB -Replacing 500 mm Premo Pipes from Sethukulam to Vadanappally Ganeshamangalam Sump |
|---|---|
| Project Code | TCRGOK04181359P6 |
| Type | Package |
| Main Project | KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | CWSS to Nattika Firka -Replacing 500 mm Premo Pipes from Sethukulam to Vadanappally Ganeshamangalam Sump |
| Status | On-going |
| District | Thrissur |
| Executing Office | Vadanappalli Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 194000000 |
| TS Number | TS/2019-2020/2018/9096 |
| Technical specification | Replacing 500 mm Premo Pipes from Sethukulam to Vadanappally Ganeshamangalam Sump |
| Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
|---|---|---|---|---|---|---|
| 31 Aug 2021 | Pending | Pending | Road Cut Related Risk | Road cutting sanction not obtained from PWD. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 26/08/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 23 Feb 2021 |
| Expected date of Completion | 31/10/2022 |
| TS Date | 26 Aug 2019 |
|---|---|
| Estimate Approval | 26 Aug 2019 |
| NIT Approval | 26 Aug 2019 |
| Tender Closing | 16 Oct 2019 |
| Technichal Pre-Qualification | 17 Oct 2019 |
| Price bid opening | 18 Oct 2019 |
| Workorder Date | 24 Feb 2020 |
|---|---|
| NA | 08 Sep 2020 |
| Vadanappilly AE |
| Date: 01/07/2026 |
Work in progress | 20% Completed
Package 6 (Sri. Paulose) terminated under Risk & Cost. Work retendered and work status updated in package 7.
| Vadanappilly AE |
| Date: 20/06/2026 |
Work in progress | 20% Completed
Package 6 (Sri. Paulose) terminated under Risk & Cost. Work retendered and work status updated in package 7.