KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle
Project |
KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle |
Project Code |
TCRKIIFB04181359 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB -Project-(TRAN2-WRD005-127):Replacement of Transmission Mains in Thrissur Circle |
Status |
On-going |
District |
Thrissur |
Executing Office |
Irinjalakkuda PH Dn |
AS Amount (Rs) |
351400000
|
AS Number |
APR-4/401/2018/KIIFB |
TS Amount (Rs) |
194000000 |
TS Number |
TS/2019-2020/2018/9096 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
170328 |
Capacity in MLD |
20.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
A Comprehensive Water Supply Scheme to Nattika Firka, commissioned during 1990, is meant
for supplying water to Ten panchayaths under the coastal belt. The Source of scheme is
Karuvannur river. The present capacity of the treatment plant at Vellani is 20 MLD. The scheme
caters to 10 panchayaths. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Project-III-KIIFB - Replacing 450 mm AC pipes with 450 mm DI-K9 from Illikkadu Valve chamber to Vazhakunnu church in Chalakudy municipality |
Chalakkudy PH Sn |
|
2 |
Project-II-KIIFB -Replacing 500 mm Premo pipes by laying 500 mm DI -K9 pipes from C.V centre to Agastheswaram temple - Reach -1 |
Mathilakam PH Sn |
|
3 |
Project-IV-KIIFB - Replacing 400 mm Premo pipes by laying 400 mm DI -K9 pipes from Agastheswaram temple to Mathilakam Sump. |
Mathilakam PH Sn |
|
4 |
Project No.I-KIIFB-Replacing 400 mm AC pipes with 400 mm DI-K9 from Vazhakunnu Chruch to Urumbankunnu centre in Chalakudy municipality |
Chalakkudy PH Sn |
|
5 |
Project VI KIIFB -Replacing 500 mm Premo Pipes from Sethukulam to Vadanappally Ganeshamangalam Sump |
Vadanappalli Sn |
|
6 |
Project-V-KIIFB -Replacing 350 mm AC pipes with 350 mm DI-K9 from Asarippara to Potta Pappali junction . |
Chalakkudy PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 May 2024 |
KIIFB-TRANS2-WRD005-127-PROJECT2-CWSS TO NATTIKA FIRKA- Replacing 500mm Premo Pipes by Laying 500mm DI K9 pipes from CV Centre to Agastheswaram Temple- REACH I-Pipeline Work- TS Issued by CE |
Mathilakam AE |
|
23 Apr 2024 |
KIIFB-TRANS2-WRD005-127-PROJECT2-CWSS TO NATTIKA FIRKA- Replacing 500mm Premo Pipes by Laying 500mm DI K9 pipes from CV Centre to Agastheswaram Temple- REACH I-Pipeline Work- TS Issued by CE |
Mathilakam AE |
|
17 Apr 2024 |
KIIFB-TRANS2-WRD005-127-PROJECT2-CWSS TO NATTIKA FIRKA- Replacing 500mm Premo Pipes by Laying 500mm DI K9 pipes from CV Centre to Agastheswaram Temple- REACH I-Pipeline Work- TS Issued by CE |
Mathilakam AE |
|
04 Apr 2024 |
KIIFB-TRANS2-WRD005-127-PROJECT2-CWSS TO NATTIKA FIRKA- Replacing 500mm Premo Pipes by Laying 500mm DI K9 pipes from CV Centre to Agastheswaram Temple- REACH I-Pipeline Work- TS Issued by CE |
Mathilakam AE |
|
27 Mar 2024 |
KIIFB-TRANS2-WRD005-127-PROJECT2-CWSS TO NATTIKA FIRKA- Replacing 500mm Premo Pipes by Laying 500mm DI K9 pipes from CV Centre to Agastheswaram Temple- REACH I-Pipeline Work- TS Issued by CE |
Mathilakam AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/04/2018 |
Scheduled date of Completion of the Project |
23 Feb 2021 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
09 Apr 2018 |
TS Date |
26 Aug 2019 |