DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work
| Project |
DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work |
| Project Code |
KLMDEPO032314033 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Urban Water Supply Scheme – Others |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-QWSS in Kollam -: Urban
Agglomaration-Extension of 90mm and 63mm
PVC pipe line at Div No 5 Vallikeezhu.-
Pipeline Work |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Kollam WS Sub Dn |
| AS Amount (Rs) |
573520
|
| AS Number |
PC8/12005/23 |
| TS Amount (Rs) |
573520 |
| TS Number |
WRD/KWA-CE(SR)/EST_TS/8555/2023_26_1_1 |
| Total Bill Submitted (Rs) |
340416 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
250 |
| Capacity in MLD |
7.20 |
| Actual Project Completion Date |
29 Jun 2023 |
| Coverage |
Div No 5 Vallikeezhu.-
|
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-QWSS in Kollam -: Urban Agglomaration-Extension of 90mm and 63mm PVC pipe line at Div No 5 Vallikeezhu.- Pipeline Work |
Kollam WS Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 24 Jun 2023 |
100 % completed |
Kollam WS Sn 2 - AE |
|
| 22 Jun 2023 |
Pipe laying work completed. Restoration of concrete to be done . |
Kollam WS Sn 2 - AE |
|
| 20 Jun 2023 |
96% completed, Pipe laying cannot possible in water logged area due to rain . |
Kollam WS Sn 2 - AE |
|
| 16 Jun 2023 |
96%completed |
Kollam WS Sn 2 - AE |
|
| 12 Jun 2023 |
96 % completed |
Kollam WS Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
23/03/2023 |
| Scheduled date of Completion of the Project |
31 May 2023 |
| Expected date of Completion |
31/05/2023 |
Processing Dates
| AS Date |
23 Mar 2023 |
| TS Date |
10 Apr 2023 |