| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2023 | 100 % completed | Kollam WS Sn 2 - AE | |
| 22 Jun 2023 | Pipe laying work completed. Restoration of concrete to be done . | Kollam WS Sn 2 - AE | |
| 20 Jun 2023 | 96% completed, Pipe laying cannot possible in water logged area due to rain . | Kollam WS Sn 2 - AE | |
| 16 Jun 2023 | 96%completed | Kollam WS Sn 2 - AE | |
| 12 Jun 2023 | 96 % completed | Kollam WS Sn 2 - AE | |
| 09 Jun 2023 | 90 % completed | Kollam WS Sn 2 - AE | |
| 07 Jun 2023 | Work started today morning. | Kollam WS Sn 2 - AE | |
| 05 Jun 2023 | Site handed over and work will start soon. | Kollam WS Sn 2 - AE | |
| 01 Jun 2023 | Tested pipe not received | Kollam WS Sn 2 - AE | |
| 29 May 2023 | Tested pipe not received | Kollam WS Sn 2 - AE |