AMRUT -Kannur Corporation - Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD
| Project |
AMRUT -Kannur Corporation - Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD |
| Project Code |
KNRAMRUT11173110 |
| Type |
Main project |
| Funding Agency |
AMRUT |
| Category |
AMRUT |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD |
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Kannur Project Dn |
| AS Amount (Rs) |
78000000
|
| AS Number |
|
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
75753598 |
| Total Bill Paid (Rs) |
75753598 |
| Population Benefitted |
45442 |
| Capacity in MLD |
10.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
45442(Population)
9752(Habitation) |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT -Kannur Corporation - Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD-Package -I |
Kannur Project Dn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 23 Nov 2020 |
work completed on 30.10.2020 |
Koothuparamba Project Sn No 1 |
|
| 16 Nov 2020 |
Completed and trial running in progress |
Koothuparamba Project Sn No 1 |
|
| 13 Sep 2020 |
95% works completed. Some mechanical works remaining. |
Koothuparamba Project Sn No 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
06/04/2018 |
| Scheduled date of Completion of the Project |
16 May 2019 |
| Expected date of Completion |
30/10/2020 |
Processing Dates
| AS Date |
02 Nov 2017 |
| TS Date |
27 Nov 2017 |
| Estimate Approval |
27 Nov 2017 |
| Tender Closing |
26 Feb 2018 |
| Technichal Pre-Qualification |
21 Mar 2018 |
| Price bid opening |
21 Mar 2018 |
Approval Dates
| Head Office Approval |
11 May 2018 |
| Workorder Date |
17 May 2018 |
| NA |
02 Jun 2018 |