Project | AMRUT -Kannur Corporation - Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD-Package -I |
---|---|
Project Code | KNRAMRUT11173110P1 |
Type | Package |
Main Project | AMRUT -Kannur Corporation - Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Enhancing Capacity of Treatment Plant in Chavassery Paramba from 30 MLD to 40 MLD |
Status | Completed |
District | Kannur |
Executing Office | Kannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/04/2018 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 30/10/2020 |
AS Date | 02 Nov 2017 |
---|---|
TS Date | 27 Nov 2017 |
Estimate Approval | 27 Nov 2017 |
Workorder Date | 17 May 2018 |
---|---|
NA | 02 Jun 2018 |
Koothuparamba Project Sn No 1 |
Date: 16/11/2020 |
Work has been completed | 100% Completed
Completed and trial running in progress.
Koothuparamba Project Sn No 1 |
Date: 30/09/2020 |
Work in progress | 97% Completed
Trial running started..