Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DW-Kochi Corporation -Replacing the existing 63 mm PVC pipe in construction of canal side wall with supplying and laying new 63 mm HDPEb pipe (8 kg/cm2) for a length of 65 m at Edappally -Arakkakadavu road in Div no:34 (old) of Kochi Corporation.

Project DW-Kochi Corporation -Replacing the existing 63 mm PVC pipe in construction of canal side wall with supplying and laying new 63 mm HDPEb pipe (8 kg/cm2) for a length of 65 m at Edappally -Arakkakadavu road in Div no:34 (old) of Kochi Corporation.
Project Code EKMDEPO03218808P1
Type Package
Main Project DW-Kochi Corporation -Replacing the existing 63 mm PVC pipe in construction of canal side wall with supplying and laying new 63 mm HDPEb pipe (8 kg/cm2) for a length of 65 m at Edappally -Arakkakadavu road in Div no:34 (old) of Kochi Corporation.
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DW-Kochi Corporation -Replacing the existing 63 mm PVC pipe in construction of canal side wall with supplying and laying new 63 mm HDPEb pipe (8 kg/cm2) for a length of 65 m at Edappally -Arakkakadavu road in Div no:34 (old) of Kochi Corporation.
Status On-going
District Ernakulam
Executing Office Kaloor WW Sn1
Agreement Number
Agreement Date
TS Amount (Rs) 35000
TS Number TS/2021-2022/2020/9317
Technical specification DW-Kochi Corporation -Replacing the existing 63 mm PVC pipe in construction of canal side wall with supplying and laying new 63 mm HDPEb pipe (8 kg/cm2) for a length of 65 m at Edappally -Arakkakadavu road in Div no:34 (old) of Kochi Corporation.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/03/2022
Scheduled date of Completion as per agreement 15 Apr 2022
Expected date of Completion 31/07/2023

Processing Dates

TS Date 07 Dec 2021
Estimate Approval 07 Dec 2021
NIT Approval 10 Dec 2021
Tender Closing 17 Dec 2021
Technichal Pre-Qualification 18 Dec 2021
Price bid opening 20 Dec 2021

Approval Dates

Workorder Date 13 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaloor AE 1
Date: 14/05/2024

Work in progress | 10% Completed

Contractor not willing, work may dropped.

Kaloor AE 1
Date: 07/05/2024

Work in progress | 10% Completed

Contractor not willing, work may dropped.