AMRUT 2.0 - ALUVA MUNICIPALITY
Project |
AMRUT 2.0 - ALUVA MUNICIPALITY |
Project Code |
EKMAMRUT2112214144 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT 2.0 - ALUVA MUNICIPALITY - Providing new house connections in various wards of Aluva Municipality, Replacing old damaged AC/CI/GI pipes and allied works, Shifting of existing water connections to new lines, Supply and fixing of valves at various locations, Supplying and installing pump sets at Water Treatment Plant, Aluva etc. |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
13610000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
13610000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/895/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
22428 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
All wards of Aluva municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 - ALUVA MUNICIPALITY |
Aluva Pipeline Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 May 2024 |
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited. |
Aluva AE I PL Sn |
|
02 May 2024 |
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited. |
Aluva AE I PL Sn |
|
29 Apr 2024 |
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited. |
Aluva AE I PL Sn |
|
26 Apr 2024 |
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited. |
Aluva AE I PL Sn |
|
22 Apr 2024 |
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited. |
Aluva AE I PL Sn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/03/2023 |
Scheduled date of Completion of the Project |
30 Jun 2023 |
Expected date of Completion |
31/05/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
30 Jan 2023 |