AMRUT 2.0 - ALUVA MUNICIPALITY

Project AMRUT 2.0 - ALUVA MUNICIPALITY
Project Code EKMAMRUT112214144P1
Type Package
Main Project AMRUT 2.0 - ALUVA MUNICIPALITY
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT 2.0 - ALUVA MUNICIPALITY-Providing new house connections in various wards of Aluva Municipality, Replacing old damaged AC/CI/GI pipes and allied works, Shifting of existing water connections to new lines, Supply and fixing of valves at various locations, Supplying and installing pump sets at Water Treatment Plant, Aluva etc.
Status On-going
District Ernakulam
Executing Office Aluva Pipeline Sn
Agreement Number
Agreement Date
TS Amount (Rs) 13610000
TS Number WRD/KWA-CE(CR)/EST_TS/895/2022_26_1_1
Technical specification Providing new house connections in various wards of Aluva Municipality, Replacing old damaged AC/CI/GI pipes and allied works, Shifting of existing water connections to new lines, Supply and fixing of valves at various locations, Supplying and installing pump sets at Water Treatment Plant, Aluva etc.
Contractor National Electrical works (Mob: 9847514062)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/03/2023
Scheduled date of Completion as per agreement 30 Jun 2023
Expected date of Completion 30/06/2023

Processing Dates

TS Date 30 Jan 2023
Estimate Approval 30 Jan 2023
Tender Closing 01 Mar 2023
Price bid opening 02 Mar 2023

Approval Dates

Workorder Date 31 Mar 2023
NA 12 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Aluva AE I PL Sn
Date: 18/05/2024

Work in progress | 70% Completed

Project Status Updation Update status Last updation Work in progress | 70% Completed | 14/05/2024 Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited..

Aluva AE I PL Sn
Date: 14/05/2024

Work in progress | 70% Completed

Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited..