Project | AMRUT 2.0 - ALUVA MUNICIPALITY |
---|---|
Project Code | EKMAMRUT112214144P1 |
Type | Package |
Main Project | AMRUT 2.0 - ALUVA MUNICIPALITY |
Funding Agency | AMRUT 2 |
Category | AMRUT 2 |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT 2.0 - ALUVA MUNICIPALITY-Providing new house connections in various wards of Aluva Municipality, Replacing old damaged AC/CI/GI pipes and allied works, Shifting of existing water connections to new lines, Supply and fixing of valves at various locations, Supplying and installing pump sets at Water Treatment Plant, Aluva etc. |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva Pipeline Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 13610000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/895/2022_26_1_1 |
Technical specification | Providing new house connections in various wards of Aluva Municipality, Replacing old damaged AC/CI/GI pipes and allied works, Shifting of existing water connections to new lines, Supply and fixing of valves at various locations, Supplying and installing pump sets at Water Treatment Plant, Aluva etc. |
Contractor | National Electrical works (Mob: 9847514062) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 30 Jun 2023 |
Expected date of Completion | 30/06/2023 |
TS Date | 30 Jan 2023 |
---|---|
Estimate Approval | 30 Jan 2023 |
Tender Closing | 01 Mar 2023 |
Price bid opening | 02 Mar 2023 |
Workorder Date | 31 Mar 2023 |
---|---|
NA | 12 Apr 2023 |
Aluva AE I PL Sn |
Date: 18/05/2024 |
Work in progress | 70% Completed
Project Status Updation Update status Last updation Work in progress | 70% Completed | 14/05/2024 Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited..
Aluva AE I PL Sn |
Date: 14/05/2024 |
Work in progress | 70% Completed
Applied in ROW portal on 28/4/23 for municipal road cutting sanction for laying PVC pipes. Factory inspection of pumpset completed on 8/7/23. Pumpset supplied by contractor and the erection work of Pumpsets completed. 166 out of 500 FHTCs given of which 164 bill submitted. All pipes are supplied.. 90 mm PVC laying completed (120 m) and 110 mm PVC pipelaying work completed.Third part bill submittited..