JJM 2020-21- Setting up/upgradation/Operation of Laboratories-Modernisation of Q C Dt Lab Aluva
Project |
JJM 2020-21- Setting up/upgradation/Operation of Laboratories-Modernisation of Q C Dt Lab Aluva |
Project Code |
EKMJJM08203468 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Modernisation of Dt Lab Ernakulam at Aluva and setting up Bacteriology Lab to meet NABL criteria, flooring works in sample collection and sample and chemical store rooms etc |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi QC Dn |
AS Amount (Rs) |
1150000
|
AS Number |
|
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
1043867 |
Total Bill Paid (Rs) |
1043867 |
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
NA |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM 2020-21- Setting up/upgradation/Operation of Laboratories-Modernisation of Q C Dt Lab Aluva |
QC division kochi |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Feb 2021 |
Bill settled |
Kochi QC Dn EE |
|
13 Feb 2021 |
bill submitted to HO on 12.02.2021 |
Kochi QC Dn EE |
|
10 Feb 2021 |
Completed. Bill submitted to Dn on 09.02.2021 |
Kochi QC Dn EE |
|
27 Jan 2021 |
work completed |
Kochi QC Dn EE |
|
23 Nov 2020 |
work in progress and propose to complete by 15th January |
Kochi QC Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/11/2020 |
Scheduled date of Completion of the Project |
08 Jan 2021 |
Expected date of Completion |
05/01/2021 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
13 Sep 2020 |
Estimate Approval |
13 Sep 2020 |
NIT Approval |
17 Sep 2020 |
Tender Closing |
30 Sep 2020 |
Price bid opening |
03 Oct 2020 |
Approval Dates
Workorder Date |
09 Oct 2020 |
NA |
22 Oct 2020 |