Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Feb 2021 Bill settled Kochi QC Dn EE
13 Feb 2021 bill submitted to HO on 12.02.2021 Kochi QC Dn EE
10 Feb 2021 Completed. Bill submitted to Dn on 09.02.2021 Kochi QC Dn EE
27 Jan 2021 work completed Kochi QC Dn EE
23 Nov 2020 work in progress and propose to complete by 15th January Kochi QC Dn EE