BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Pkg2- Distribution system

Project BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Pkg2- Distribution system
Project Code MLPKIIFB1118517P2
Type Package
Main Project Budget 2017-18 KIIFB- Tranche - 10 - WRD 025- 25 Manjeri Suburban Drinking Water Project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description The work includes the CWPM to Thadaparambu, CWGM to Elembra OHSR, Distribution System to payyanad area, CWPM to OHSR Cherani etc.
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 439600000
TS Number TS/2020-2021/2020/20180, Dated: 13-10-2020
Technical specification The work include in this package as follows (i) For Clear water pumping main from Cherani sump to OHT Thadaparamba - 400 mm DI K9 - 3750 m, 250 mm DI K9 - 30 m (ii) For Clear water gravity main from OHT Thadaparamba to OHSR Elembra - 400 mm DI K9 - 4270 m, 250 mm DI K9 - 20 m (iii) For Clear water pumping main from Cherani sump to Existing OHT Cherani - 600 mm DI K9 - 520.50 m, 250 mm DI K9 - 30 m For Dedicated line to Manjeri Medical college from OHSR Thadaparamba - 150 mm DI - 2180 m (iv)For Distribution System 400 mm DI - K9 - 1590 m 350 mm DI - K9 - 510 m 300 mm DI - 2705 m 250 mm DI - 3585 m 200 mm DI - 3740 m 160 mm PVC Cl 4 - 27366m, Class 5 - 52040m , Class 6 - 2459m 110 mm PVC Class 5 - 14280 m 150 mm GI pipe - 3620 m In addition to this, renovation of existing WTP at Areacode, Intake arrangement at RWPump house are included.
Contractor REENA ENGINEERS & CONTRACTORS PVT LTD (Mob: 9544144862)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
23 Jan 2021 Pending Pending Road Cut Related Risk Road cutting permission denied No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/02/2021
Scheduled date of Completion as per agreement 31 Dec 2023
Expected date of Completion 31/03/2025

Processing Dates

TS Date 13 Oct 2020
Estimate Approval 13 Oct 2019
NIT Approval 13 Oct 2020
Tender Closing 03 Dec 2020
Technichal Pre-Qualification 11 Dec 2020
Price bid opening 18 Dec 2020

Approval Dates

Workorder Date 23 Jan 2021
NA 22 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE2
Date: 26/05/2024

Work in progress | 35% Completed

Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed, 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. 100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes in high court. KIIB Decision to be obtained for short closing the work.

Malappuram Project Dn AE2
Date: 23/05/2024

Work in progress | 35% Completed

Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed, 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. 100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes in high court. KIIB Decision to be obtained for short closing the work.