- Home
- BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-02...
BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Pkg2- Distribution system
Project |
BUDGET 2017 - 18 - KIIFB: Tran-10-WRD-025-25-MANJERI SUBURBAN DRINKING WATER PROJECT IMPROVEMENTSAND AUGMENTATION OF UWSS TO MANJERIMUNICIPALITY INCLUDING WATER SUPPLYARRANGEMENTS TO PAYYANADAND THADAPPARAMBA AREA OF MANJERI MUNICIPALITY, MALAPPURAM DISTRICT- Pkg2- Distribution system |
Project Code |
MLPKIIFB1118517P2 |
Type |
Package |
Main Project |
Budget 2017-18 KIIFB- Tranche - 10 - WRD 025- 25 Manjeri Suburban Drinking Water Project
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
The work includes the CWPM to Thadaparambu, CWGM to Elembra OHSR, Distribution System to payyanad area, CWPM to OHSR Cherani etc. |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
439600000 |
TS Number |
TS/2020-2021/2020/20180, Dated: 13-10-2020 |
Technical specification |
The work include in this package as follows
(i) For Clear water pumping main from Cherani sump to OHT Thadaparamba - 400 mm DI K9 - 3750 m, 250 mm DI K9 - 30 m
(ii) For Clear water gravity main from OHT Thadaparamba to OHSR Elembra - 400 mm DI K9 - 4270 m, 250 mm DI K9 - 20 m
(iii) For Clear water pumping main from Cherani sump to Existing OHT Cherani - 600 mm DI K9 - 520.50 m, 250 mm DI K9 - 30 m
For Dedicated line to Manjeri Medical college from OHSR Thadaparamba - 150 mm DI - 2180 m
(iv)For Distribution System
400 mm DI - K9 - 1590 m
350 mm DI - K9 - 510 m
300 mm DI - 2705 m
250 mm DI - 3585 m
200 mm DI - 3740 m
160 mm PVC Cl 4 - 27366m, Class 5 - 52040m , Class 6 - 2459m
110 mm PVC Class 5 - 14280 m
150 mm GI pipe - 3620 m
In addition to this, renovation of existing WTP at Areacode, Intake arrangement at RWPump house are included. |
Contractor |
REENA ENGINEERS & CONTRACTORS PVT LTD (Mob: 9544144862) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
23 Jan 2021 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission denied |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/02/2021 |
Scheduled date of Completion as per agreement |
31 Dec 2023 |
Expected date of Completion |
31/03/2025 |
Processing Dates
TS Date |
13 Oct 2020 |
Estimate Approval |
13 Oct 2019 |
NIT Approval |
13 Oct 2020 |
Tender Closing |
03 Dec 2020 |
Technichal Pre-Qualification |
11 Dec 2020 |
Price bid opening |
18 Dec 2020 |
Approval Dates
Workorder Date |
23 Jan 2021 |
NA |
22 Feb 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE2 |
Date: 26/05/2024 |
Work in progress | 35% Completed
Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed, 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. 100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes in high court. KIIB Decision to be obtained for short closing the work.
Malappuram Project Dn AE2 |
Date: 23/05/2024 |
Work in progress | 35% Completed
Laying work of 400 mm DI pumping main from Cherani SUMP to Thadaparamba OHSR completed, 2). Laying of 400mm of gravity main from Thadaparamba OHSR to Elambra OHSR completed, 3). Laying of 600mm DI pumping main from cherani sump to cherani OHSR completed, 4). 400 mm DI and 300 mm DI Pipe line distribution with PVC rider main laying work started . 5) Laying of PVC Distribution pipe lines from Thadaparamba OHSR progressing. , 6) distribution from Elambra OHSR pending . PWD/KRFB permission pending in Manjeri Olipuzha road for the laying of distribution main and medical college line. 100 km PVC pipes to be supplied by contractor . Contractor filed a petition for an increase in the rate of PVC pipes in high court. KIIB Decision to be obtained for short closing the work.