Amrut 2.0-UWSS to Kayamkulam Municipality
Project |
Amrut 2.0-UWSS to Kayamkulam Municipality |
Project Code |
ALPAMRUT2112213098 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Amrut 2.0-UWSS to Kayamkulam Municipality Phase I - Prviding 4400 nos. FHTC, Construction of 12 LL OHSR, Laying of conveyance main |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
AS Amount (Rs) |
198870000
|
AS Number |
GO (Rt) No. 2906/2022/LSGD Dated 24/11/2022 |
TS Amount (Rs) |
191350000 |
TS Number |
16349/2022-2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
38525 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Kayamkulam Municipal Area |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Amrut 2.0-UWSS to Kayamkulam Municipality Phase I |
Alappuzha Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. |
Alappuzha Project Dn PM |
|
22 Apr 2024 |
Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. |
Alappuzha Project Dn PM |
|
19 Apr 2024 |
Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. |
Alappuzha Project Dn PM |
|
16 Apr 2024 |
Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. |
Alappuzha Project Dn PM |
|
11 Apr 2024 |
Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. |
Alappuzha Project Dn PM |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
16 Mar 2023 |