Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. Alappuzha Project Dn PM
22 Apr 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. Alappuzha Project Dn PM
19 Apr 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. Alappuzha Project Dn PM
16 Apr 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. Alappuzha Project Dn PM
11 Apr 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. Design obtained from WASCON and the estimate revision was completed and forwarded to CE(CR) on 15/04/2024. TS obtained for pipeline work and is Tendered. Alappuzha Project Dn PM
06 Apr 2024 Sent to PQ approval Alappuzha Project Dn PM
20 Mar 2024 Sent to PQ approval Alappuzha Project Dn PM
21 Feb 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. TS obtained work is Tendered Alappuzha Project Dn PM
12 Feb 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. TS obtained work is Tendered Alappuzha Project Dn PM
29 Jan 2024 Pipe line work including FHTCs & Construction of 15LL OHSR at Kayamakulam is seperately arranged. TS obtained for Pipe line work with FHTCs & For Construction of OHSR work, CE (CR) directed to provide design drawings and hence request was forwarded to Desing Wing , WASCON. TS obtained work is Tendered, due date on 05-02-2024 Alappuzha Project Dn PM