| Project | State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
|---|---|
| Project Code | KNRGOK052517438P1 |
| Type | Package |
| Main Project | State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
| Status | On-going |
| District | Kannur |
| Executing Office | Pilathra WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| Thaliparamba WS Dn EE |
| Date: 09/01/2026 |
Work in progress | 0% Completed
ender stage.
| Pilathara WS Sn - AE |
| Date: 23/12/2025 |
Work has started | 0% Completed
Tender stage.