- Home
- State Plan 2025-26-Replacing damaged val...
State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara
| Project |
State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
| Project Code |
KNRGOK052517438 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
| Status |
On-going |
| District |
Kannur |
| Executing Office |
Pilathra WS Sn |
| AS Amount (Rs) |
500000
|
| AS Number |
KWA-JB/3465/2025-AE-Part(1) |
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
State Plan 2025-26-Replacing damaged valves in various distribution lines under WS Section Pilathara |
Pilathra WS Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 23 Dec 2025 |
Tender stage |
Pilathara WS Sn - AE |
|
| 22 Dec 2025 |
Tender stage |
Pilathara WS Sn - AE |
|
| 20 Dec 2025 |
Tender stage |
Pilathara WS Sn - AE |
|
| 20 Jun 2025 |
Tender stage |
Pilathara WS Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
Date is not specified |