JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP

Project JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP
Project Code KNRJJM092110806P1
Type Package
Main Project JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description A 200 mm DI common gravity main is proposed from existing 28 LL GLSR of WSS to Koothuparamba to the existing Sump at Pathipalam as an interim measure for summer days as existing source dries up in summer.
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 67200000
TS Number 15812/2021-22
Technical specification Laying 200 MM DI K9 gravity main 9000 m at 28 LL existing GLSR at Valiyavelicham to sump at Pathipalam
Contractor Mariya Constructions (Mob: 9446643423)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/03/2022
Scheduled date of Completion as per agreement 24 Jun 2022
Expected date of Completion 28/02/2024

Processing Dates

TS Date 21 Dec 2021
Estimate Approval 21 Dec 2021
NIT Approval 24 Feb 2022
Tender Closing 27 Jan 2022
Technichal Pre-Qualification 27 Jan 2022
Price bid opening 29 Jan 2022

Approval Dates

Workorder Date 25 Feb 2022
NA 03 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 14/03/2024

Work has been completed | 100% Completed

Successfully completed the Trial Running and Testiing from the common gravity main from GLSR VALIYAVELICHAM to Sump at Pathippalam WTP.

Mattannur Project Sn 2 AE
Date: 08/03/2024

Work in progress | 99% Completed

Trial Running and Testing completed.Commissioning is in progress.