Project | JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP |
---|---|
Project Code | KNRJJM092110806P1 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | A 200 mm DI common gravity main is proposed from existing 28 LL GLSR of WSS to Koothuparamba to the existing Sump at Pathipalam as an interim measure for summer days as existing source dries up in summer. |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 67200000 |
TS Number | 15812/2021-22 |
Technical specification | Laying 200 MM DI K9 gravity main 9000 m at 28 LL existing GLSR at Valiyavelicham to sump at Pathipalam |
Contractor | Mariya Constructions (Mob: 9446643423) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 24 Jun 2022 |
Expected date of Completion | 28/02/2024 |
TS Date | 21 Dec 2021 |
---|---|
Estimate Approval | 21 Dec 2021 |
NIT Approval | 24 Feb 2022 |
Tender Closing | 27 Jan 2022 |
Technichal Pre-Qualification | 27 Jan 2022 |
Price bid opening | 29 Jan 2022 |
Workorder Date | 25 Feb 2022 |
---|---|
NA | 03 Mar 2022 |
Mattannur Project Sn 2 AE |
Date: 14/03/2024 |
Work has been completed | 100% Completed
Successfully completed the Trial Running and Testiing from the common gravity main from GLSR VALIYAVELICHAM to Sump at Pathippalam WTP.
Mattannur Project Sn 2 AE |
Date: 08/03/2024 |
Work in progress | 99% Completed
Trial Running and Testing completed.Commissioning is in progress.