JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP

Project JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP
Project Code KNRJJM092110806
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description A 200 mm DI common gravity main is proposed from existing 28 LL GLSR of WSS to Koothuparamba to the existing Sump at Pathipalam as an interim measure for summer days as existing source dries up in summer.
Status On-going
District Kannur
Executing Office Mattannur Project Dn
AS Amount (Rs) 67200000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 67200000
TS Number 15812/2021-22
Total Bill Submitted (Rs) 55031335
Total Bill Paid (Rs) 55031335
Population Benefitted 26816
Capacity in MLD 1.70
Actual Project Completion Date Date is not specified
Coverage Panniyannur & Mokeri Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-KANNUR DISTRICT-WSS TO PANNIYANNUR PANOOR AND MOKERI PHASE-III -APPENDIX-A- COMMON GRAVITY MAIN FROM GLSR AT VALIYAVELICHAM TO SUMP AT PATHIPALAM WTP Mattannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jul 2023 200 mm DI K9 8748.5m supplied and 8336m laid Mattannur Project Sn 2 AE
04 Aug 2022 200 mm DI K9 8748.5m supplied and 620m laid Mattannur Project Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/03/2022
Scheduled date of Completion of the Project 24 Jun 2022
Expected date of Completion 30/06/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 21 Dec 2021

Other details

Project Officers View