Project | Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
---|---|
Project Code | ALPDEPO122213708P1 |
Type | Package |
Main Project | Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
Status | On-going |
District | Alappuzha |
Executing Office | Cherthala PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 420000 |
TS Number | 12065/2022-23 |
Technical specification | Pipe line extension work in Muhamma Panchayath |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 07 Jun 2023 |
Expected date of Completion | 31/12/2023 |
TS Date | 27 Jan 2023 |
---|---|
Estimate Approval | 27 Jan 2023 |
NIT Approval | 01 Feb 2023 |
Tender Closing | 14 Feb 2023 |
Price bid opening | 15 Feb 2023 |
Workorder Date | 25 Feb 2023 |
---|---|
NA | 04 Mar 2023 |
Cherthala PH Section - AE |
Date: 30/12/2023 |
Work has been completed | 100% Completed
work completed .
Cherthala PH Section - AE |
Date: 18/10/2023 |
Work in progress | 80% Completed
80% work completed .remaining work delayed due to private property consent issues.