- Deposit Work- Aryad Block panchayath-. A...
Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath
Project |
Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
Project Code |
ALPDEPO122213708 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Cherthala PH Sn |
AS Amount (Rs) |
0
|
AS Number |
25/2022-23 |
TS Amount (Rs) |
420000 |
TS Number |
12065/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Ward No. 10 and 16 of Muhamma Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work- Aryad Block panchayath-. Annual Plan 2022/23 - (Project No:15/23) .- Supplying and Laying 90 mm (6kg/cm2) PVC pipe line in ward 10 and 16 of Muhamma Panchayath |
Cherthala PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Dec 2023 |
work completed final bill submitted to subdivision |
Cherthala PH Section - AE |
|
30 Dec 2023 |
work completed |
Cherthala PH Section - AE |
|
18 Oct 2023 |
80% work completed .remaining work delayed due to private property consent issues |
Cherthala PH Section - AE |
|
02 Aug 2023 |
work in progress |
Cherthala PH Section - AE |
|
27 Jul 2023 |
Agreement executed and site handed over |
Cherthala PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
07 Jun 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
31 Dec 2022 |
TS Date |
27 Jan 2023 |