- Home
- DEPOSIT-Kochi Corporation-Newly laying 9...
DEPOSIT-Kochi Corporation-Newly laying 90mm Pvc pipe (6kg/cm2) at vyloppilly lane div 37 (old) 64 part (New) of Kochi Corpoation-Pipeline Work
Project |
DEPOSIT-Kochi Corporation-Newly laying 90mm Pvc pipe (6kg/cm2) at vyloppilly lane div 37 (old) 64 part (New) of Kochi Corpoation-Pipeline Work |
Project Code |
EKMDEPO112215000 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Kochi Corporation-Newly laying 90mm Pvc pipe (6kg/cm2) at Vyloppilly lane div 37 (old) 64 part (New) of Kochi Corpoation-Pipeline Work |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Vytilla Section 2 |
AS Amount (Rs) |
700000
|
AS Number |
A7-1831/2022 |
TS Amount (Rs) |
700000 |
TS Number |
6449/2023-2024 |
Total Bill Submitted (Rs) |
413936 |
Total Bill Paid (Rs) |
413936 |
Population Benefitted |
300 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
12 Dec 2023 |
Coverage |
DEPOSIT-Kochi Corporation-Newly laying 90mm Pvc pipe (6kg/cm2) at Vyloppilly lane div 37 (old) 64 part (New) of Kochi Corpoation-Pipeline Work |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Kochi Corporation-Newly laying 90mm Pvc pipe (6kg/cm2) at vyloppilly lane div 37 (old) 64 part (New) of Kochi Corpoation-Pipeline Work |
Vytilla Section 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jan 2024 |
Bill submitted on 16.01.24 |
Vytilla Section AE - 2 |
|
12 Jan 2024 |
Work completed |
Vytilla Section AE - 2 |
|
28 Dec 2023 |
work completed |
Vytilla Section AE - 2 |
|
23 Dec 2023 |
work completed |
Vytilla Section AE - 2 |
|
07 Dec 2023 |
Vyloppilli road restoration work completed |
Vytilla Section AE - 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/09/2023 |
Scheduled date of Completion of the Project |
12 Dec 2023 |
Expected date of Completion |
12/12/2023 |
Processing Dates
AS Date |
28 Nov 2022 |
TS Date |
16 Jun 2023 |