Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Jan 2024 | Bill submitted on 16.01.24 | Vytilla Section AE - 2 | |
12 Jan 2024 | Work completed | Vytilla Section AE - 2 | |
28 Dec 2023 | work completed | Vytilla Section AE - 2 | |
23 Dec 2023 | work completed | Vytilla Section AE - 2 | |
07 Dec 2023 | Vyloppilli road restoration work completed | Vytilla Section AE - 2 | |
25 Nov 2023 | Restoration work going on | Vytilla Section AE - 2 | |
13 Nov 2023 | Pipe laying going on | Vytilla Section AE - 2 | |
09 Nov 2023 | Pipe laying | Vytilla Section AE - 2 |