CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH .
Project |
CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH . |
Project Code |
EKMDEPO02229223 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
CSME |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH . |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
290000
|
AS Number |
A2-2021/33716 |
TS Amount (Rs) |
290000 |
TS Number |
TS/2021-2022/2021/33716 Dated: 26-02-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
200 |
Capacity in MLD |
0.20 |
Actual Project Completion Date |
11 Aug 2022 |
Coverage |
15 NOS Villas |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH |
Aluva PH Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Aug 2022 |
Bill to be submitted |
Aluva PH S Dn AEE |
|
28 Aug 2022 |
Work completed |
Aluva AE PH Sn 2 |
|
25 Aug 2022 |
work completed |
Aluva AE PH Sn 2 |
|
23 Aug 2022 |
work completed |
Aluva AE PH Sn 2 |
|
22 Aug 2022 |
work completed |
Aluva AE PH Sn 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/03/2022 |
Scheduled date of Completion of the Project |
17 Jun 2022 |
Expected date of Completion |
17/06/2022 |
Processing Dates
AS Date |
25 Feb 2022 |
TS Date |
26 Feb 2022 |