Project | CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH |
---|---|
Project Code | EKMDEPO02229223P1 |
Type | Package |
Main Project | CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH . |
Funding Agency | DEPO |
Category | CSME |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | CSME DEPOSIT WORK -EXTENSION OF PIPE LINE FOR PROVIDING WATER CONNECTION TO 15 NOS VILLA PROJECT FOR MR.THOMAS THOMAS IN WARD 3 OF CHOORNIKKARA PANCHAYATH |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva PH Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 290000 |
TS Number | TS/2021-2022/2021/33716 Dated: 26-02-2022 |
Technical specification | 90 mm dia Pipe line extension - 177 m |
Contractor | Viji Elias (Mob: 9847606022) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 17 Jun 2022 |
Expected date of Completion | 17/06/2022 |
TS Date | 26 Feb 2022 |
---|---|
Estimate Approval | 26 Feb 2022 |
NIT Approval | 28 Feb 2022 |
Tender Closing | 08 Mar 2022 |
Technichal Pre-Qualification | 12 Mar 2022 |
Price bid opening | 11 Mar 2022 |
Workorder Date | 15 Mar 2022 |
---|---|
NA | 23 Mar 2022 |
Aluva AE PH Sn 2 |
Date: 28/08/2022 |
Work has been completed | 100% Completed
Work completed.
Aluva AE PH Sn 2 |
Date: 26/08/2022 |
Work has been completed | 100% Completed
Work completed.