| Project | NABARD RIDF XX - WSS To Ongallur and Vallappuzha Panchayaths-Laying Distribution 600DI Gravity main from WTP to Main road |
|---|---|
| Project Code | PKDNABARD0315672P1 |
| Type | Package |
| Main Project | NABARD- RIDF- XX - WSS To Ongallur and Vallappuzha Panchayats in Pattambi Taluk in Palakkad district |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | Laying 600mm DI Gravity main for a length of 880m and 160mm PVC pipe for a length of 101m by using balance fund |
| Status | On-going |
| District | Palakkad |
| Executing Office | Palakkad Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 15300442 |
| TS Number | 2019-20/2019/14798 dtd.05/11/19 |
| Technical specification | Laying 600mm DI Gravity main for a length of 880m and 160mm PVC pipe for a length of 101m |
| Contractor | M/S Minartech Developers Pvt. Ltd (Mob: 9446683721) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/02/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Sep 2020 |
| Expected date of Completion | 15/10/2021 |
| TS Date | 05 Nov 2019 |
|---|---|
| Estimate Approval | 05 Nov 2019 |
| NIT Approval | 07 Nov 2019 |
| Tender Closing | 29 Jan 2020 |
| Technichal Pre-Qualification | 31 Jan 2020 |
| Price bid opening | 31 Jan 2020 |
| NA | 29 Feb 2020 |
|---|---|
| Workorder Date | 15 Feb 2020 |
| Palakkad Proj AE 3 |
| Date: 30/09/2021 |
Work has been completed | 100% Completed
All works Completed.
| Palakkad Project Dn AEE3 |
| Date: 22/09/2021 |
Work in progress | 82% Completed
On going .