NABARD RIDF XX - WSS To Ongallur and Vallappuzha Panchayaths-Laying Distribution 600DI Gravity main from WTP to Main road

Project NABARD RIDF XX - WSS To Ongallur and Vallappuzha Panchayaths-Laying Distribution 600DI Gravity main from WTP to Main road
Project Code PKDNABARD0315672P1
Type Package
Main Project NABARD- RIDF- XX - WSS To Ongallur and Vallappuzha Panchayats in Pattambi Taluk in Palakkad district
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Laying 600mm DI Gravity main for a length of 880m and 160mm PVC pipe for a length of 101m by using balance fund
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 15300442
TS Number 2019-20/2019/14798 dtd.05/11/19
Technical specification Laying 600mm DI Gravity main for a length of 880m and 160mm PVC pipe for a length of 101m
Contractor M/S Minartech Developers Pvt. Ltd (Mob: 9446683721)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/02/2020
Scheduled date of Completion as per agreement 30 Sep 2020
Expected date of Completion 15/10/2021

Processing Dates

TS Date 05 Nov 2019
Estimate Approval 05 Nov 2019
NIT Approval 07 Nov 2019
Tender Closing 29 Jan 2020
Technichal Pre-Qualification 31 Jan 2020
Price bid opening 31 Jan 2020

Approval Dates

NA 29 Feb 2020
Workorder Date 15 Feb 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 30/09/2021

Work has been completed | 100% Completed

All works Completed.

Palakkad Project Dn AEE3
Date: 22/09/2021

Work in progress | 82% Completed

On going .