| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 21 Mar 2021 |
WTP and intake well - major structural works completed, filter bed tile works ongoing, plastering works ongoing, mechanical electrical works pending, pumping main interconnection, pump erection, transformer installation works pending.
Distribution line 400m laying completed |
Palakkad Project Dn AEE3 |
|
| 16 Feb 2021 |
1. Intake well- R.C.C. Roof slab shuttering work in progress . 2. Raw water pumping main 400mm DI- Laying completed till the plant site boundary (3661.39mtr). 3.10MLD Plant . Clarifoculator-works completed ,32LL CWR - Roof slab Partially completed, Filter house structural works completed, Wash water tank RCC upto roof slab completed , Base slab of aerator completed, Approach road - Road formation completed, Side protection with RR masonry completed for one side, Quarry muck filling completed. 6. Chemical store and chlorine room masonry works completed. 7. Porch and office room Plastering completed. 8. Boundary protection work 50% completed for one side. 9. Plastering for CWR inside completed, Laboratory RCC & brick work completed, Compressor room & panel room upto roof slab completed.Flash mixer, Alum & lime tank works in progress. |
Palakkad Project Dn AEE3 |
|
| 15 Feb 2021 |
1. Intake well- R.C.C. Roof slab shuttering work in progress . 2. Raw water pumping main 400mm DI- Laying completed till the plant site boundary (3661.39mtr). 3.10MLD Plant . Clarifoculator-works completed ,32LL CWR - Roof slab Partially completed, Filter house structural works completed, Wash water tank RCC upto roof slab completed , Base slab of aerator completed, Approach road - Road formation completed, Side protection with RR masonry completed for one side, Quarry muck filling completed. 6. Chemical store and chlorine room masonry works completed. 7. Porch and office room Plastering completed. 8. Boundary protection work 50% completed for one side. 9. Plastering for CWR inside completed, Laboratory RCC & brick work completed, Compressor room & panel room upto roof slab completed.Flash mixer, Alum & lime tank works in progress. |
Palakkad Project Dn AEE3 |
|
| 11 Feb 2021 |
1. Intake well- R.C.C. Roof slab shuttering work in progress . 2. Raw water pumping main 400mm DI- Laying completed till the plant site boundary (3661.39mtr). 3.10MLD Plant . Clarifoculator-works completed ,32LL CWR - Roof slab Partially completed, Filter house structural works completed, Wash water tank RCC upto roof slab completed , Base slab of aerator completed, Approach road - Road formation completed, Side protection with RR masonry completed for one side, Quarry muck filling completed. 6. Chemical store and chlorine room masonry works completed. 7. Porch and office room Plastering completed. 8. Boundary protection work 50% completed for one side. 9. Plastering for CWR inside completed, Laboratory RCC & brick work completed, Compressor room & panel room upto roof slab completed.Flash mixer, Alum & lime tank works in progress. |
Palakkad Project Dn AEE3 |
|
| 10 Feb 2021 |
1. Intake well- R.C.C. Roof slab shuttering work in progress . 2. Raw water pumping main 400mm DI- Laying completed till the plant site boundary (3661.39mtr). 3.10MLD Plant . Clarifoculator-works completed ,32LL CWR - Roof slab Partially completed, Filter house structural works completed, Wash water tank RCC upto roof slab completed , Base slab of aerator completed, Approach road - Road formation completed, Side protection with RR masonry completed for one side, Quarry muck filling completed. 6. Chemical store and chlorine room masonry works completed. 7. Porch and office room Plastering completed. 8. Boundary protection work 50% completed for one side. 9. Plastering for CWR inside completed, Laboratory RCC & brick work completed, Compressor room & panel room upto roof slab completed.Flash mixer, Alum & lime tank works in progress. |
Palakkad Project Dn AEE3 |
|