Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath

Project DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath
Project Code ALPDEPO032314251
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath
Status Completed
District Alappuzha
Executing Office Cherthala PH Sn
AS Amount (Rs) 223000
AS Number 06/2023
TS Amount (Rs) 223000
TS Number 17883/2022-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 10
Capacity in MLD 107.00
Actual Project Completion Date 07 Jun 2023
Coverage Muhamma panchayath area
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath Cherthala PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Aug 2023 Final bill submitted to Division for payment Cherthala PH SUb Dn
05 Aug 2023 Work completed and final bill received sub division Cherthala PH SUb Dn
02 Aug 2023 Completed, but bill not submitted from Section Office Cherthala PH Section - AE
27 Jul 2023 Completed, but bill not submitted from Section Office Cherthala PH Section - AE
07 Jun 2023 100% Cherthala PH Section - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 01 Jul 2023
Expected date of Completion 01/07/2023

Processing Dates

AS Date 14 Mar 2023
TS Date 30 Mar 2023

Other details

Project Officers View