Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath

Project DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath
Project Code ALPDEPO032314251P1
Type Package
Main Project DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work Muhamma Panchayath-permanent disconnection of existing public Taps( 141 Nos ) at Muhamma Panchayath
Status Completed
District Alappuzha
Executing Office Cherthala PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 223000
TS Number 17883/2022-2023
Technical specification Disconnection of public taps

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 01 Jul 2023
Expected date of Completion 01/07/2023

Processing Dates

TS Date 30 Mar 2023
Estimate Approval 30 Mar 2023
NIT Approval 30 Mar 2023
Tender Closing 13 Apr 2023
Technichal Pre-Qualification 16 Jun 2023
Price bid opening 17 Apr 2023

Approval Dates

Workorder Date 20 Apr 2023
NA 02 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Cherthala PH SUb Dn
Date: 21/08/2023

Work has been completed | 100% Completed

Bill submitted to Division for payment.

Cherthala PH SUb Dn
Date: 05/08/2023

Work has been completed | 100% Completed

Final bill received.