KIIFB - CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.

Project KIIFB - CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Project Code TVMKIIFB04186107P1
Type Package
Main Project KIIFB -Project 5- CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Status On-going
District Thiruvananthapuram
Executing Office Kallara Sn
Agreement Number
Agreement Date
TS Amount (Rs) 20815000
TS Number 6891/2023-2024
Technical specification Replacement of ACpipes

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/07/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/12/2022

Processing Dates

TS Date 22 Jun 2023
Estimate Approval 22 Jun 2023
NIT Approval 22 Jun 2023

Approval Dates

Workorder Date 25 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kallara AE
Date: 15/07/2024

Work has been completed | 100% Completed

completed.

Kallara AE
Date: 08/07/2024

Work in progress | 99% Completed

pipe laying and road concreting completed.