KIIFB -Project 5- CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.

Project KIIFB -Project 5- CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Project Code TVMKIIFB04186107
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Status On-going
District Thiruvananthapuram
Executing Office Kallara Sn
AS Amount (Rs) 10400000
AS Number APR-4/401/2018/KIIFB
TS Amount (Rs) 10400000
TS Number 6891/2023-2024
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 0.80
Actual Project Completion Date 24 Jun 2024
Coverage 700 FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB - CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe. Kallara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2024 Anticipated date of completion 30may 2024 Kallara AE
07 May 2024 Anticipated date of completion 30may 2024 Kallara AE
03 May 2024 ongoing Kallara AE
29 Apr 2024 ongoing Kallara AE
23 Apr 2024 DI and 90 mm PVC laying work ongoing Kallara AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/11/2021
Scheduled date of Completion of the Project 31 May 2022
Expected date of Completion 30/04/2024

Processing Dates

AS Date 07 Oct 2019
TS Date 15 Oct 2021

Other details

Project Officers View