KIIFB -Project 5- CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe.
Project |
KIIFB -Project 5- CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe. |
Project Code |
TVMKIIFB04186107 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe
and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kallara Sn |
AS Amount (Rs) |
10400000
|
AS Number |
APR-4/401/2018/KIIFB |
TS Amount (Rs) |
10400000 |
TS Number |
6891/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.80 |
Actual Project Completion Date |
24 Jun 2024 |
Coverage |
700 FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB - CWSS to Kallara and Pangode Panchayaths - Replacing 300 mm AC pipeline along Nellimukku Iyyermukku(Thannichal) road with 300 mm DI K9 pipe and Replacing 125 mm AC pipe near Paluvalli and Vattakkarikkakom with 140 mm PVC 10 Kg/cm2 pipe. |
Kallara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 May 2024 |
Anticipated date of completion 30may 2024 |
Kallara AE |
|
07 May 2024 |
Anticipated date of completion 30may 2024 |
Kallara AE |
|
03 May 2024 |
ongoing |
Kallara AE |
|
29 Apr 2024 |
ongoing |
Kallara AE |
|
23 Apr 2024 |
DI and 90 mm PVC laying work ongoing |
Kallara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/11/2021 |
Scheduled date of Completion of the Project |
31 May 2022 |
Expected date of Completion |
30/04/2024 |
Processing Dates
AS Date |
07 Oct 2019 |
TS Date |
15 Oct 2021 |