| Project | AWSS TO KOLLAM CORPORATION -Extension of distribution system for a total of 50 Kms in various zones using PVC pipes, including road restoration charges (Phase 1) |
|---|---|
| Project Code | KLMAMRUT112214153P8 |
| Type | Package |
| Main Project | AMRUT - 2.0 - Augmentation of Water Supply To Kollam Corporation – Distribution Improvements |
| Funding Agency | AMRUT |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | Extension of distribution system for a total of 50 Kms in various zones using PVC pipes, including road restoration charges (Phase 1) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 37873 |
| TS Number | No.8344/2023-24 |
| Technical specification | |
| Contractor | Sohail shamsudeen (Mob: 9809509114) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/05/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 25 Nov 2024 |
| Expected date of Completion | 25/11/2024 |
| TS Date | 11 Jul 2023 |
|---|---|
| Price bid opening | 27 Oct 2023 |
| NA | 26 Feb 2024 |
|---|
| Kollam Project Dn EE |
| Date: 05/02/2026 |
Work has been completed | 100% Completed
Work 100% completed on 04/02/2026. .